Keyword Search:
 
Home
Breaking News
Local News
Statewide News
Feature Articles
Ferrell Friend
News Links

Breaking News:


4/10/07-House Fire Causes Injuries
   Shortly before 3:00 am this morning, the home of Rosalee Keen, which is owned by Avis and Don Moore, caught fire.
   Keen suffered burn injuries and was flown to the burn center in Pittsburgh.
   Sources were unable to confirm whether or not Keen made it out of the home on her own or whether she was rescued.
   The fire burned through telephone and internet lines, cutting off service, including emergency 911 lines. Frontier crews were called in by Sheriff Randy Holcomb as soon as the problem was recognized and hare still working as of 2:00 pm.
   Though not as severely damaged, the home next to Keen’s was also irreversibly damaged by heat and smoke.
   Also, Crews had been working on putting out the flames for several hours when an explosion was heard and felt. According to Greg Fitzwater, Clay VFD Chief, a medical oxygen tank was heated to the point of exploding. No one was injured during the blast.
   The West Virginia Fire Marshal’s Office and the Federal ATF Bureau are investigating the blaze.

3/19/07-CLAY COUNTY FLOODPLAIN ORDINANCE

AN ORDINANCE ESTABLISHING A FLOODPLAIN AREA AND REQUIRING ALL CONTRACTORS, PERSONS, PARTNERSHIPS, BUSINESSES, AND CORPORATIONS TO OBTAIN A PERMIT FOR DEVELOPMENT AND THE CONSTRUCTION, SUBSTANTIAL IMPROVEMENT , OR RELOCATION OF ANY BUILDING OR STRUCTURE; PROVIDNG FOR CERTAIN MINIMUM STANDARDS FOR CONSTRUCTION WITHIN THE FLOODPLAIN AREA AND SETTING FORTH SPECIAL PROCEDURES FOR SUBMISSION AND APPROVAL OF PLANS; AND ESTABLISHING PENALTIES FOR ANY PERSON WHO FAILS TO COMPLY WITH THE REQUIREMENTS OR PROVISIONS OF THIS ORDINANCE.

BE IT ENACTED AND ORDAINED by the Clay County Commission as follow:

ARTICLE I - GENERAL PROVISIONS

      Section 1.1 Intent

 The intent of this ordinance is to:

A. Promote the general health, welfare, and safety of the community.

B. Encourage the utilization of appropriate construction practices in order to prevent or minimize flood damage in the future.

C. Minimize danger to public health and safety by protecting water supply and sanitary sewage disposal in cooperation with the County Sanitarian, and to protect natural drainage.

D. Assure the County Assessor obtains information concerning improvement of real property as required by WV State Code 11-3-3A.

E. Assure County E-911 addresses are obtained to maintain the currency of established emergency response dispatch systems.

F. Reduce financial burdens imposed on the community, its governmental units, and its residents, by preventing the unwise design and construction of development in areas subject to flooding.

Section 1.2 Abrogation and Greater Restrictions

This ordinance supersedes any ordinance currently in effect in flood prone areas.  Any ordinance, however, shall remain in full force and effect to the extent that its provisions are more restrictive.

 

      Section 1.3 Applicability

It shall be unlawful for any contractor, person, partnership, business, or corporation to undertake or cause to be undertaken, any development, new construction, substantial improvement, repair of substantial damage, or the placement or relocation of any structure (including manufactured homes) within Clay County, unless a permit application has been completed and a permit and certificate of compliance has been obtained from the Floodplain Administrator.  In addition, where land is to be subdivided, utilized for a manufactured home park or subdivision or otherwise developed, a site plan must be submitted to, and approved by, the Floodplain Administrator prior to any development.

Provision of all other codes, ordinances, and regulations shall be applicable insofar as they are consistent with the provisions of this ordinance and the community’s need to minimize the hazards and damage resulting from flooding.

      Section 1.4 Matters not provided for specifically

Where conditions are encountered that are not specifically provided for herein, the floodplain administrator shall determine the applicability of the provisions of this ordinance in accordance with its intent, and shall require the applicant to take appropriate measures pursuant to such determination.


ARTICLE II - INTERPRETATIONS AND DEFINITIONS

Section 2.1 Interpretations

A. For the purpose of this ordinance, the following interpretations shall apply:

1. Words used in the present tense include the future tense

2. The singular includes the plural.

3. The plural includes the singular.

4. The Term “shall” or “will” is always mandatory.

5. The word “building” or “structure” shall be construed as if followed by the phrase “or part thereof”.

6. The word “Ordinance” shall refer to the Floodplain Ordinance.

Section 2.2 Definitions

      General

Unless specifically defined below, words and phrases used in this ordinance shall be interpreted so as to give this ordinance it’s most reasonable application.

 

Appurtenant Structure

A structure on the same parcel of property as the principal structure and the use of which is incidental to the use of the principal structure.  This does not include a gas or liquid storage tank.

Base Flood

The flood, which has been selected to serve as the basis upon which the floodplain management provisions of this and other ordinances have been prepared; for purposes of this ordinance, the one-hundred (100) year flood.

Basement

Any area of the building having its floor sub grade (below ground level) on all sides.

Certificate of Compliance

A certification that the entire development, including the elevation of fill or the lowest floor of a structure is in compliance with all of the provisions of this ordinance.

Contractor - WV State Code 21-11-3(c)

A person who in any capacity for compensation, other than as an employee of another, undertakes, offers to undertake, purports to have the capacity to undertake, or submits a bid to construct, alter, repair, add to, subtract from, improve, move, wreck or demolish any building, highway, road, railroad, structure or excavation associated with a project, development or improvement, or to do any part thereof, including the erection of scaffolding or other structures or works in connection therewith, where the cost of the undertaking is one thousand dollars or more.  Contractor includes a construction manager who performs management and counseling services on a construction project for a professional fee.

Contractor does not include:

(1) One who merely furnishes materials or supplies without fabricating or consuming them in the construction project.

(2) A person who personally performs construction work on the site of real property which the person owns or leases whether for commercial or residential purposes;

(3) A person who is licensed or registered as a professional and who functions under the control of any other licensing or regulatory board, whose primary business is real estate sales, appraisal, development, management and maintenance, who acting in his or her respective professional capacity and any employee of such professional, acting in the course of his or her employment, performs any work which may be considered to be performing contracting work

(4) A pest control operator licensed under the provisions of section seven, article sixteen-a, chapter nineteen of this code to engage in the application of pesticides for hire, unless the operator also performs structural repairs exceeding one thousand dollars on property treated for insect pests; or

(5) A corporation, partnership or sole proprietorship whose primary purpose is to prepare construction plans and specifications used by the contractors defined in this section and who employs full time a registered architect licensed to practice in this state or a registered professional engineer licensed to practice in this state. Contractor also does not include employees of such corporation, partnership or sole proprietorship.

Development

Any man-made change to improved or unimproved real estate, including but not limited to buildings or other structures, mining, dredging, filling, grading, paving, excavation or drilling operations or storage of equipment or materials.

Flood

A general and temporary inundation of normally dry land areas.

Floodplain

(1) A relatively flat or low land area adjoining a river, stream, or watercourse which is subject to partial or complete inundation;

(2)  An area subject to the unusual and rapid accumulation or runoff of surface waters from any source.

Floodplain Administrator

The Clay County Emergency Services Director shall be the floodplain Administrator.  The Floodplain Administrator may delegate this authority to others as deemed appropriate. The Floodplain Administrator may also be identified as the Floodplain Manager.

Floodway

The channel of a river or other watercourse and the adjacent land area that must be reserved to discharge the base flood without increasing the water surface elevation of that flood more than one foot at any point.

Flood proofing

Any combination of structural and non-structural additions, changes or adjustments to structures which reduce or eliminate flood damage to real estate or improved real property, water and sanitary facilities, structures and their contents.

Freeboard

A factor of safety usually expressed in feet above a flood level for purposes of floodplain management. Freeboard tends to compensate for unknown factors that may contribute uncertainty to flood heights of any given flood and floodway condition, such as wave action, blockage at stream crossings, and increased runoff from urbanization of the watershed.

Historic Structure

Any structure that is:

(a) Listed individually in the National Register of Historic Places (a listing maintained by the Department of Interior) or preliminarily determined by the Secretary of the Interior as meeting the requirements for individual listing on the National Register;

(b) Certified or preliminarily determined by the Secretary of the Interior as contributing to the historical significance of a registered historic district or a district preliminarily determined by the Secretary to qualify as a registered historic district

(c) Individually listed on a state inventory of historic places in states with historic preservation programs which have been approved by the Secretary of the Interior; or,

(d) Individually listed on a local inventory of historic places in communities with historic preservation programs that have been certified either:

(i) By an approved state program as determined by the Secretary of the Interior; or,

(ii) Directly by the Secretary of Interior in states without approved programs.

 Licensed Manufactured Home Dealer

A business licensed to sell Manufactured Homes in the state of WV as set forth in the WV state code.

Licensed Manufacturing Home Installer

A contractor licensed to install Manufactured Homes in WV as set forth in the WV State Code.

Licensed Professional Surveyor

Any person licensed by the WV state board of examiners of land surveyors to engage in the practice of land surveying as defined in WV state code.


Lowest Floor

The lowest floor of the lowest enclosed area (including basement).  An unfinished enclosure constructed with flood resistant materials as defined in the FEMA Technical Bulletin 2-93 (FIA-TB-2) and usable solely for parking of vehicles, building access or storage in an area other than a basement area is not considered a building’s lowest floor; Provided, that such enclosure is not built so as to render the structure in violation of the applicable non-elevation design requirements of this ordinance.

Manufactured Home

A structure, transportable in one or more sections, which is built on a permanent chassis and is designed for use with or without a permanent foundation when connected to the required utilities.  The term “manufactured home” does not include a “recreational vehicle”.

New Construction

Structures for which the Start of Construction as herein defined commenced on or after November 26, 1990 and including any subsequent improvements to such structures.

One-Hundred (100) Year Flood

A flood that has one chance in one-hundred or a one percent chance of being equaled or exceeded in any given year.
      Practice of Engineering
Any service or creative work, as described in WV state code Article 13, the adequate performance of which requires engineering education, training and experience in the application of special knowledge of the mathematical, physical and engineering sciences to such services or creative work as consultation, investigation, evaluation, planning and design of engineering works and systems; planning the use of land and water; teaching of advanced engineering subjects, engineering surveys and studies; and the review of construction for the purpose of assuring compliance with drawings and specifications any of which embraces such services or work, either public or private, in connection with any utilities, structures, buildings, machines, equipment, processes, work systems, projects and industrial or consumer products or equipment of a mechanical, electrical, hydraulic, pneumatic or thermal nature, insofar as they involve safeguarding life, health or property, and including such other professional services as may be necessary to the planning, progress and completion of any engineering services. Engineering surveys include all survey activities required to support the sound conception, planning, design, construction, maintenance and operation of engineered projects.
Any person who practices any branch of the profession of engineering or who, by verbal claim, sign, advertisement, letterhead, card or in any other way represents himself or herself to be a registered professional engineer, or by using another title implies that he or she is a registered professional engineer or that he or she is registered under WV state code, article 13 or who holds himself or herself out as able to perform, or who performs any engineering service or work or any other service designated by the practitioner which is recognized as engineering, is considered to practice or offer to practice engineering within the meaning and intent of WV state code article 13.

Person

Any individual or group of individuals, corporation, partnership, association or other entity, including State and local governments and agencies.

Principally Above Ground

Where at least 51 percent of the actual cash value of a structure, less land value, is above ground.

Recreational Vehicle

A vehicle which is:

(a) built on a single chassis; (b) 400 square feet or less when measured at the largest horizontal projection; (c) designed to be self-propelled or permanently towable by a light duty truck; and (d) designed primarily not for use as a permanent dwelling but as temporary living quarters for recreational, camping, travel, or seasonal use.

Registered professional engineer

A person who has been duly registered or licensed as a registered professional engineer by the West Virginia state board of registration for professional engineers as required under WV state code article 13 et seq.

      Remedy a Violation

To bring a structure or other development into compliance with the requirements of this ordinance, or, if full compliance is not possible, to reduce the adverse impacts of the non-compliance to the greatest extent feasible.

Reasonably Safe from Flooding

Means base flood waters will not inundate the land or damage structures to be removed from the special flood hazard area and that any subsurface waters related to the base flood will not damage existing or proposed buildings.

Start of Construction (The definition for start of construction is to be used only when calculating the starting time of the 6 month expiration of a permit.)

The date the permit was issued, including permits for substantial improvement or substantial damage, provided the actual start of construction, repair, reconstruction, rehabilitation, addition, placement, or other improvement was within 180 days of the permit date.  The actual start means either the first placement of permanent construction on a site, such as the pouring of slab or footings, the installation of piles, the construction of columns, or any work beyond initial excavation, or the placement of a manufactured home on a foundation.  Although a permit must be obtained prior to beginning, permanent construction does not include land preparation, such as clearing, grading and filling, nor does it include the installation of streets and/or walkways, nor does it include excavation for a basement, footings, piers or foundations or the erection of temporary forms, nor does it include the installation on the property of accessory buildings, such as garages or sheds not occupied as dwelling units or not part of the main structure.  For an alteration, the actual start of construction means the first alteration of any wall, ceiling, floor or other structural part of a building, whether or not that alteration affects the external dimensions of the building.

State Coordinating Office

The West Virginia Division of Homeland Security and Emergency Management

Stream

As defined in WV State Code 7-1-3U, any watercourse, whether natural or man-made, distinguishable by banks and a bed, regardless of their size, through which water flows continually or intermittently, regardless of its volume.

Structure

A walled and roofed building, including a gas or liquid storage tank that is principally above ground, as well as a manufactured home.

Substantial Damage

Damage of any origin sustained by a structure whereby the cost of restoring the structure to its before damage condition would equal or exceed 50 percent of the market value of the structure before the damage occurred.  Substantial damage also means cumulative flood-related damages sustained by a structure on two separate occasions during a 10 year period for which the cost of repairs at the time
of each flood event equals or exceeds 25 percent of the market value of the structure before the damage occurred.  See “Substantial Improvement.”

Substantial Improvement

Any repair, reconstruction, rehabilitation, addition, or other improvement of a structure, the cost of which equals or exceeds 50 percent of the market value of the structure before the Start of Construction of the improvement. 

This term includes structures, which have incurred “substantial damage”, as defined herein regardless of the actual repair work performed.  The term does not, however, include any project for improvement of a structure to correct existing violation of state or local health, sanitary or safety code specifications which have been identified by the local code enforcement official and which are the minimum necessary to assure safe living conditions. (continued next page)

Historic structures undergoing repair or rehabilitation that would constitute a substantial improvement as defined above, must comply with all ordinance requirements that do not preclude the structure’s continued designation as a historic structure. Documentation that a specific ordinance requirement will cause removal of the structure from the National Register of Historic Places or the State Inventory of Historic places must be obtained from the Secretary of the Interior or the State Historic Preservation Officer. Any exemption from ordinance requirements will be the minimum necessary to preserve the historic character and design of the structure.
 
For the purpose of this definition improvement is considered to occur when the first alteration of any wall, ceiling, floor or other structural part of the building commences whether or not that alteration affects the external dimensions of the structure.

Top of Bank

The lines depicted on the FIRM maps delineating each side of a stream indicate the top of bank. In the field a professional familiar with fluvial geomorphology should document the top of bank. When a professional is not employed the top of the bank will be considered to be the top of the first significant slope landward of the waters edge when it is followed by at least 50 feet of relatively flat land.

Violation

The failure of any structure or development to be fully compliant with all requirements of this ordinance.

ARTICLE III - ESTABLISHMENT OF THE FLOODPLAIN AREA

 Section 3.1 Identification
 
A. The identified floodplain area shall be those areas of the Clay County which are subject to the one hundred (100) year flood, as shown on the Flood Insurance Rate Map (FIRM) and described in the Flood Insurance Study (FIS) prepared for Clay County by the Federal Emergency Management Agency (FEMA) dated March 18, 1991 or the most recent revision thereof.

B. The identified floodplain area shall also be those areas of Clay County which have been identified as flood hazard areas by Clay County by use of historic or other technical data and shown on the Clay County “Local Flood Hazards Map”. These areas shall be designated as appropriate with the level of technical data described below and shall be managed accordingly.
     
Section 3.2 Descriptions of Floodplain Areas

The identified floodplain shall consist of the following four specific areas:

A. The Floodway area (F1) shall be those areas identified as such in the FIS and as shown on the floodway map or FIRM. The term shall also include floodway areas identified in other studies for the approximated area discussed in Section D Below.  (continued next page)
In studied floodplain areas for which no regulatory floodway has been designated, the regulatory floodway for small, single lot development not incorporating significant amounts of fill can, at the discretion of the community, be considered to be the channel of the stream and the adjacent land areas to a distance of one-half the width of the floodplain as measured from the top of the bank nearest the site to the upland limit of the 100 year floodplain boundary.


B. The Floodway Fringe area (F2) shall be those areas for which specific one hundred (100) year flood elevations have been provided in the FIS but which lie beyond the floodway area. 

C. The AE Area without Floodway (F3) shall be those areas identified as an AE Zone on the FIRM included in the FIS prepared by FEMA for which 100-year flood elevations have been provided but no Floodway has been delineated.
     
            D.  The Approximated area (F4) shall be those areas identified as an A Zone    on the FIRM or floodway map included in the FIS prepared by FEMA and   for which no one hundred (100) year flood elevations have been provided.    For these areas, elevation and floodway information from other Federal,    State, or other acceptable source shall be used when available.  Where    other acceptable information is not available the Floodplain Administrator    shall require the applicant to determine the elevation with hydrologic and    hydraulic engineering or other techniques.  When hydrologic and     hydraulic analyses are required, they shall only be undertaken by     professional engineers or others of demonstrated qualifications, who shall    certify that the methods used correctly reflect currently accepted technical    concepts.  The resultant study shall include a cover letter, signed by the    responsible professional, providing a statement of findings in basic terms.    In addition, studies, analyses, computations, etc. shall be submitted in    sufficient detail to allow a thorough technical review by the floodplain    administrator.

Section 3.3 Changes in Designation of Area

A. The delineation of the identified floodplain area may be revised by the Clay County Commission where natural or man-made changes have occurred and/or more detailed studies conducted or undertaken by the U.S. Army Corps of Engineers, a River Basin Commission or other qualified agency or individual document the necessity for such changes.  However, prior to any such change, approval must be obtained from the Federal Insurance Administration (FIA).

B. The Clay County Commission may identify and regulate new flood hazard or ponding areas. These areas may be delineated using locally derived technical information such as flood of record, historic high water marks and/or topographic data. 

 

Section 3.4 Elevations Prevail

A. If the lowest natural grade adjacent to the foundation of a proposed building within an identified flood hazard area is at or above the Base Flood Elevation specified in the Flood Insurance Study, the structure shall not be required to conform to the flood prevention design and construction standards or flood-related development codes in Article VI.  Topographic data certified by a registered professional engineer or surveyor shall be submitted in sufficient detail to allow a thorough review by the Floodplain Administrator.  The applicant is advised to apply for a Letter of Map Amendment (LOMA) from FEMA to have the Special Flood Hazard Area designation removed from the parcel or structure. 

B. If the lowest natural grade adjacent to the foundation of a proposed building is below the Base Flood Elevation specified in the Flood Insurance Study, the site shall be considered to be within the floodplain area and the proposed structure shall be required to conform to all appropriate provisions of this ordinance.

Section 3.5 Boundary Disputes

Should a dispute concerning any district boundary arise, an initial determination shall be made by the Floodplain Administrator and any party aggrieved by this decision may appeal to the Clay County Commission.  The burden of proof shall be on the appellant/applicant.

ARTICLE IV - UTILIZATION OF THE FLOODPLAIN AREA

Section 4.1 Floodway (F1)

A. Within any floodway area (F1), no encroachments, including fill, new construction, substantial improvements, repair of substantial damage, or other development shall be permitted unless it has been demonstrated through hydrologic and hydraulic analysis performed in accordance with standard engineering practice that the proposed encroachment will not result in any increase in the Base Flood Elevation. 

B. Because floodways present increased risk to human life and property because of their relatively faster and deeper flowing waters the Floodway shall be preserved to the greatest extent possible. 

1. New development shall not be permitted in the floodway where reasonable alternatives exist elsewhere. In addition to the requirements below the applicant shall demonstrate that there are no reasonable alternatives other than the floodway encroachment before a permit is issued. 

2. When the floodway is the only reasonable alternative the applicant shall demonstrate that the floodway encroachment is the minimum necessary to accomplish the project.

C. All permitted uses, activities, and development shall be undertaken in strict compliance with the flood proofing and related provisions contained herein, and in all other applicable codes, ordinances and regulations.

Section 4.2 Floodway Fringe (F2) and Approximated Floodplain (F4)

A. In the Floodway Fringe (F2) and Approximated Floodplain (F4), any development and/or use of land shall be permitted provided that all such uses, activities and/or development shall be undertaken in strict compliance with the flood-proofing and related provisions contained herein and in all other applicable codes, ordinances and regulations. 

B. All subdivision proposals and other proposed new developments which are proposed to take place either fully or partially within the Approximated Floodplain area (F4) and which are greater than five (5) lots or one (1) acres, whichever is the lesser, shall include base flood elevation data.

1. This data may be available from an authoritative source, such as the U.S. Army Corps of Engineers, U.S. Geological Survey, Natural Resource Conservation Service or state and local water resource department.

2. If the required data is not available from other sources the applicant shall develop the technical data using detailed methodologies comparable to those contained in a Flood Insurance Study. This data shall be prepared and certified by a registered professional engineer or others of demonstrated qualifications, who shall certify that the methods used correctly reflect currently accepted technical concepts. 

C. All new or improved structures located in the Approximated Floodplain (F4) shall be elevated at least three (3) feet above the highest adjacent grade unless Base Flood Elevation data has been obtained from an authoritative source or developed by a qualified professional using a detailed methodology as described above.

Section 4.3 AE area without floodway (F3)

Within any AE area without floodway, no new construction or development shall be allowed unless it is demonstrated that the cumulative effect of the proposed development, when combined with all other existing and anticipated development, will not increase the elevation of the 100-year flood more than one (1) foot at any point.  This requirement can be satisfied by utilization of the floodway area where determined.


Section 4.4 Alteration or relocation of a stream

A.  Whenever a developer intends to alter or relocate a stream within the Floodplain Area, the developer shall notify in writing, by certified mail, the Clay County Floodplain Administrator, The State Coordinating Office and any adjacent communities of all such intended activities prior to the alteration or relocation of the stream, and shall submit copies of such notification to the Federal Insurance Administration ..  The Floodplain Administrator shall require copies of all necessary permits from those governmental agencies from which Federal or State Law requires approval prior to issuing the local permit. Contact information for State and Federal permitting authorities as well as addresses for required notification of appropriate County, State & Federal government agencies are contained in the Clay County Stream Alteration/Crossing administrative procedures.
  
B. The developer shall also assure the Floodplain Administrator in writing that the carrying capacity within the altered or relocated portion of stream will be maintained.  The Floodplain Administrator may require the applicant to demonstrate that the altered or relocated portion of stream will provide equal or greater conveyance than the original stream segment.  If hydrologic and hydraulic analyses are required, they shall only be undertaken by professional engineers or others of demonstrated qualifications, who shall certify that the methods used correctly reflect currently accepted technical concepts.  The resultant study shall include a cover letter, signed by the responsible professional, providing a statement of findings in basic terms.  In addition, studies, analyses, computations, etc. shall be submitted in sufficient detail to allow a thorough technical review by the floodplain administrator.

C. Alteration of a stream includes placement of culverts, bridges or other stream crossings. The floodplain administrator may require the use of certain “best practice” techniques in the construction of bridges, culverts or stream crossings to prevent damage or loss of stream crossings and localized flooding caused by blockages.  These techniques may include, but are not limited to, wing walls, trash grates or requiring openings to be of sufficient size to pass debris and/or anticipated future increases in flood heights.

D. All new and replacement bridges, culverts and other stream crossings shall adhere to the relevant anchoring requirements contained in this ordinance.

E. The developer is required to provide the community a legal agreement detailing all scheduled inspections and maintenance to be performed on altered or relocated watercourses including culverts, bridges and other stream crossings. It shall be the responsibility of the applicant to transfer this agreement to the new owner when the land associated with the watercourse alteration is transferred. A copy of all new agreements shall be provided to the floodplain administrator.

F. The applicant must submit any maps, computations or other material                           required by the Federal Emergency Management Agency (FEMA) to revise the Flood Insurance Study and/or Flood Insurance Rate Maps, when notified by the floodplain Administrator, and must pay any fees or other costs assessed by FEMA for this purpose.

ARTICLE V - CRITERIA FOR BUILDING AND SITE PLAN APPROVAL

Section 5.1 General

Permits are required in order to determine whether all new construction or substantial improvements are:

A.  Located in the identified Floodplain or Floodway.

B.  Designed (or modified) and adequately anchored to prevent flotation, collapse, or lateral movement of the structure resulting from hydrodynamic and hydrostatic loads, including the effects of buoyancy. 

C. Constructed with material and utility equipment resistant to flood damage as outlined in FEMA Technical Bulletin 2-93 (FIA-TB-2) or the most recent revision thereof.

D. Constructed by methods and practices that minimize flood damage.

E. Constructed with electrical, heating, ventilation, plumbing and air conditioning equipment and other service facilities that are designed and/or located so as to prevent water from entering or accumulating within the components during conditions of flooding.

Section 5.2 Basic Format

      The basic format of the permit shall include the following:

      A. Name and address of applicant

B.  Name and address of owner of land on which proposed construction is to occur.

C.  Name, address, and valid WV license number of all contractor(s), or affidavit stating that work is being performed by individuals exempt from contractor licensing as set forth in Title 28, Series 2, section 3.9 (b) of the West Virginia Code of state regulations or the most recent revision thereof.

      D.  Site location including tax map and parcel number.

E.  The contract required by WV Code of State Regulations, Title 28, Series 4, and all addendums to the contract(s) shall be presented to the floodplain administrator for review within five (5) business days of contract signing. The community does not require and will not keep copies of the contracts or addendums. Failure to present contract or addendums for review shall void the permit. If a licensed contractor is not involved or the work is of an aggregate value of less than ten thousand dollars including materials and labor, a brief written description of proposed work and the estimated value will suffice.

F. A standard site plan showing the exact size and location of the proposed development, adjacent roads and watercourses with direction of flow as well as any existing buildings or structures.

G. An acknowledgement that the applicant agrees to pay any and all fees associated with the permitting process as set forth in Section 7.9 hereof.

H. An acknowledgement that the applicant agrees to allow community officials access to the development to inspect for compliance.


Section 5.3 Elevation and Flood Proofing Information

All applicants are encouraged to exceed the minimum elevation requirements contained herein. Flood insurance rates can be lowered significantly by increasing the elevation of the lowest floor above the freeboard height required by this ordinance.

Depending on the type of structure involved, the following information shall also be included in the application for work within the Floodplain Area:

A. For structures to be elevated 18 inches above the Base Flood Elevation:

1. A site plan showing the size of the proposed structure and its relation to the lot where it is to be constructed.

2. A determination of elevations of the Base Flood, existing ground, proposed finished ground and lowest floor, certified by a Registered Professional Engineer, Surveyor, or Architect.

3. Plans showing the method of elevating the proposed structure including details of proposed fills, pile structures, retaining walls, foundations, erosion protection measures, etc.  When required by the Floodplain Administrator, a Registered Professional Engineer or Architect shall prepare these plans.

4. Plans showing the methods used to protect utilities (including sewer, water, telephone, electric, gas, etc.) from flooding to two feet above the Base Flood Elevation at the building site.

5. During the course of construction, as soon as the basic elements of the lowest floor are in place and before further vertical construction, it is highly recommended that the applicant obtain elevation data completed by a Licensed Surveyor certifying the height of the lowest floor.

6. A Nonconversion Agreement shall be signed by the applicant whenever the community determines that the area below the first floor could be converted to a non-conforming use (generally applies to areas below base flood elevation with more than 5 vertical feet).  This agreement shall state:

(i) The area below Base Flood Elevation shall not be converted for
use other than for parking, building access or for allowable storage as detailed in this ordinance.

      (ii) The applicant agrees to notify prospective buyers of the existence
      of this agreement.  It shall be the responsibility of the applicant to
      transfer the agreement at closing to the new owner via notarized
      signature, a copy of all new agreements shall be provided to the
      Floodplain Administrator.

B. For structures to be flood proofed to three feet above the Base Flood Elevation (nonresidential structures only):
  
All applicants are encouraged to exceed the minimum flood proofing     requirements contained herein. Flood insurance rates can be lowered significantly by increasing the level of flood proofing above the height required by this ordinance. In order to obtain an “elevation credited” flood insurance rate on dry flood proofed buildings, flood proofing must extend at least one foot above the Base Flood Elevation.

1. Plans showing details of all flood proofing measures, prepared by a Registered Professional Engineer or Architect, showing the size of the proposed structure and its relation to the lot where it is to be constructed.

2. A determination of elevations of the Base Flood, existing ground, proposed finished ground, lowest floor, and flood proofing limits; certified by a Registered Professional Engineer, Surveyor, or Architect.

3. A Flood proofing Certificate, FEMA 81-65, as revised by FEMA, shall be prepared by the Registered Professional Engineer or Architect who prepared the plans in (1) above, stating the structure in question, together with attendant utility and sanitary facilities is designed so that:

(i)  The structure is water tight with walls substantially impermeable to the passage of water from the lowest structural element to three feet above the Base Flood Elevation.

(ii) The structure will withstand the hydrostatic, hydrodynamic,
      buoyant, impact, and other forces resulting from the flood depths,
      velocities, pressures, and other factors associated with the Base
      Flood.

C. For structures constructed of flood resistant materials – used solely for parking of vehicles, or storage, (Appurtenant Structures only).

1. Plans showing details of all flood proofing measures and showing the size of the proposed structure and its relation to the lot where it is to be constructed.

2. A completed Elevation Certificate showing elevation of existing ground, proposed finished ground, and lowest floor.

3. A certificate must be prepared by the Floodplain Administrator, that confirms that the structure in question, together with attendant utilities is designed so that:

(i) Flood resistant materials as detailed in FEMA Technical Bulletin 2-93 (FIA-TB-2) are used in the construction of the structure from the lowest structural element to three feet above the Base Flood Elevation and that all utilities are located at least three feet above the Base Flood Elevation.

(ii) Hydrostatic flood forces on exterior walls are equalized by
      allowing for automatic entry and exit of floodwaters. Designs for
      meeting this requirement must either be certified by a Registered
      Professional Engineer or Architect or meet or exceed the following
      minimum criteria:

a) A minimum of two openings having a total net area of not less than one square inch for every square foot of enclosed area subject to flooding shall be provided.

b) The bottom of all openings shall be no higher than one foot above grade.

c) Openings may be equipped with screens, louvers, valves or other coverings or devices provided that they permit the automatic entry and exit of floodwaters.

      (iii) The applicant shall sign a Non-conversion Agreement and notify
      prospective buyers of the existence of the agreement. It shall be the  responsibility of the applicant to transfer the Non-conversion
      Agreement to any new owner at closing via notarized signature. A
      copy of the signed agreement shall be provided to the floodplain
      administrator.

Section 5.4 Site Plan Criteria

The owner or developer of any proposed development, including Subdivisions and Manufactured Home Parks, shall submit a preliminary site plan to the Floodplain Administrator that includes the following information:

A.  Name of engineer, surveyor, or other qualified person responsible for providing the information required in this section.

B. A map showing the location of the proposed subdivision and/or development with respect to the town’s floodplain areas, proposed lots sites, and fills.  In addition, it is required that all subdivision proposals and other proposed new developments which are proposed to take place either fully or partially within the approximated floodplain (F4) and which are greater that ten (10) lots or two (2) acres, whichever is the lesser, shall include base flood elevation data.  If FEMA has completed a Flood Insurance Study (FIS), that data must be used to substantiate the base flood.  Otherwise, the developer may submit data provided by an authoritative source, such as U.S. Army Corps of Engineers, U.S. Geological Survey, Natural Resources Conservation Service, state and local water resource departments, or technical data developed using detailed methodologies comparable to those contained in a Flood Insurance Study. This data shall be prepared and certified by a registered professional engineer or others of demonstrated qualifications, who shall certify that the technical methods used correctly reflect currently accepted technical concepts.

C.  Where the subdivision and/or development lies partially or completely in the floodplain areas, the plan map shall include detailed information giving the location and elevation of proposed roads, public utilities and building sites.  All such maps shall also show contours at intervals of two (2) or five (5) feet depending upon the slope of the land and identify accurately the boundaries of the floodplain areas.

D. Where the subdivision lies partially in the floodplain area and all proposed development will take place on natural grade a significant vertical distance above the floodplain area, development of detailed Base Flood Elevation data may not be necessary.  In these cases the site plan for the proposed development must clearly delineate the area to be developed and the location of the floodplain areas as depicted on the FEMA map. A registered professional engineer, licensed professional surveyor or others of demonstrated qualifications must certify the site plan.
 
 Section 5.5 – Restrictions to Subdivision of land in floodplain areas.

All lots shown on the plat must have 3,000 square feet of buildable area outside the identified flood hazard area and be served by streets within the proposed subdivision having surfaces not lower than 1 foot below the elevation of the line defining the floodplain limits. All new structures must be sited on the portion of the subdivided lot that is located outside of the identified flood hazard area.

ARTICLE VI - SPECIFIC REQUIREMENTS

Section 6.1 Design and Construction Standards

In order to prevent excessive damage to buildings, structures, and related utilities and facilities, the following restrictions apply to all development, subdivision proposals, manufactured home parks, new construction and to construction of substantial improvements, and the repair of substantial damage, to existing structures occurring in the Floodplain Area.

A. Basements and Lowest Floors

   1.   All new construction, relocation, substantial improvements, including  repair of substantial damage, of residential structures must have the lowest  floor, including basement, ductwork and utilities, elevated 18 inches above
    the Base Flood Elevation.
  
   2.  All new construction, relocation, substantial improvements, including    repair of substantial damage, of nonresidential structures must have the    lowest floor, including basement, ductwork and utilities, elevated to 18    inches above the Base Flood Elevation; or, together with attendant utility    and sanitary facilities, be designed so that the structure is water tight with    walls substantially impermeable to the passage of water from the lowest    structural element to three feet above the Base Flood Elevation.
     
      3.   For all new construction, relocation, substantial improvement, and
repair of substantial damage, those fully enclosed areas below the lowest floor that are usable solely for parking of vehicles, building access or storage in an area other than a basement and which are subject to flooding shall be designed to automatically equalize hydrostatic flood forces on exterior walls by allowing for entry and exit of floodwaters.  Designs for meeting this requirement must either be certified by a Registered Professional Engineer or meet or exceed the following minimum criteria:

(i) A minimum of two openings having a total net area of not less than one square inch for every square foot of enclosed area subject to flooding shall be provided.

(ii) The bottom of all openings shall be no higher than one foot above grade.

(iii) Openings may be equipped with screens, louvers, valves, or other coverings or devices provided that they permit the automatic entry and exit of floodwaters.

B. Manufactured Home Placement

      1.  Manufactured homes to be placed or substantially improved within flood    hazard areas shall:

(i) Be elevated so that the lowest floor, ductwork and utilities including HVAC/heat pump are elevated two feet above the Base Flood Elevation.

(ii) Be elevated on reinforced piers or other foundation elements of at least equivalent strength engineered for use in a flood hazard area and attached to a permanent foundation.

(iii) The frame shall be anchored to an adequately anchored permanent foundation system to resist flotation, collapse and lateral movement.

(iv) Installation designs incorporating dry stacked block shall not be used in flood hazard areas.

(v) Ground anchors shall not be considered permanent foundation systems.
      
2.   All manufactured homes being placed in an identified flood hazard area  shall be installed by a contractor possessing a valid WV Manufactured  Home Installer's license. The installer shall certify in writing that the  manufactured home has been installed to the standards set forth above.

C.  Appurtenant Structures

1. Except as provided in subsection 2 below, appurtenant structures shall be located out of the floodplain area or elevated to eighteen (18) inches above the Base Flood Elevation.

2. Where appurtenant structures not connected to the principal structure are to be located on sites below the Base Flood Elevation, the following flood damage reduction provisions apply:

(i) Structures shall be no more than 600 square feet in size and valued at less than $10,000.00.

(ii) Floors shall be at or above grade on at least one side.

(iii) Structures shall be located, oriented and constructed to minimize flood damage.

(iv) Structures shall be designed (or modified) and adequately anchored to prevent flotation, collapse, or lateral movement of the structure resulting from hydrodynamic and hydrostatic loads, including the effects of buoyancy.

(v) Flood resistant materials as detailed in FEMA Technical Bulletin 2-93 (FIA-TB-2) shall be used in the construction of the structure from the lowest structural element to two feet above the Base Flood Elevation.

(vi) Machinery, electric devices or appliances, and all utilities shall be located at least eighteen (18) above the Base Flood Elevation.

(vii) The venting requirements contained in Section 6.1 (A) are applicable and shall be strictly adhered to.

3. A Nonconversion Agreement shall be signed by the applicant stating that the use of the appurtenant structure or detached or attached garage shall not be changed from the use permitted, acknowledging that the structure may be subject to greater flood risk and that higher flood insurance premiums may be possible, and that a change in use may require full compliance with this ordinance.  The applicant agrees to notify prospective buyers of the existence of this agreement.  It shall be the responsibility of the applicant to transfer the agreement at closing to the new owner via notarized signature, a copy of all new agreements shall be provided to the floodplain administrator.

D. Recreational Vehicle Placement

1. Recreational vehicles to be placed within any floodplain area shall either: 
(i) Meet the provision of Section 6.1 of this ordinance or,
(ii) Be on site for fewer than 180 consecutive days or,  
(iii) Be fully licensed and ready for highway use. A recreational vehicle is ready for highway use if it is on its wheels or jacking system, is attached to the site only by quick disconnect utilities and security devices, and has no permanently attached additions. 

E. Fill

The Clay County Commission officially recognizes the beneficial functions the floodplain serves in storage and transportation of water during floods. Placement of fill in the floodplain area is discouraged and should be minimized. In the floodway, no fill shall be permitted unless it meets the requirements of Section 4.1 of this ordinance.  All fill placed in the floodplain area shall meet or exceed the following standards:

1. Fill shall be used only to the extent to which it does not adversely affect adjacent properties.  The Floodplain Administrator may require the applicant to show through hydrologic and hydraulic engineering techniques that proposed fill would not adversely affect adjacent properties.  Hydrologic and hydraulic analyses shall be undertaken only by professional engineers or others of demonstrated qualifications, who shall certify that the technical methods used correctly reflect currently accepted technical concepts.  The resultant study shall include a cover letter, signed by the responsible professional, providing a statement of findings in basic terms.  In addition, studies, analyses, computations, etc., shall be submitted in sufficient detail to allow a thorough technical review by the Floodplain Administrator.

2. Fill shall be used only to the extent to which it does not adversely affect the capacity of channels or floodways of any tributary to the main stream, drainage ditch, or any other drainage facility or system.

3. Fill shall extend beyond a structure for a sufficient distance to provide acceptable access.  For residential structures, fill shall extend laterally fifteen (15) feet beyond the building line from all points before the start of sloping required in following subsection.  For nonresidential structures, fill shall be placed to provide access acceptable for intended use.  At grade access, with fill extending laterally fifteen (15) feet beyond the building line shall be provided to a minimum of twenty-five (25) percent of the perimeter of a nonresidential structure.

4. Fill shall consist of soil or rock material only.  Sanitary landfills shall not be permitted

5. Fill material shall be compacted to provide the necessary stability and resistance to erosion, scouring or settling.

6. Fill slopes shall be no steeper than one (1) vertical on two (2) horizontal, unless substantiating data justifying steeper slopes are submitted to and approved by the Floodplain Administrator.

7. Fill slopes exposed to flood waters with expected velocities during the occurrence of the base flood of five feet per second or less must be protected from erosion by covering them with grass, vines, weeds, or similar vegetative undergrowth.

8. Fill slopes exposed to flood waters with expected velocities during the occurrence of the base flood of greater than five feet per second must be protected from erosion by armoring them with stone or rock slope protection.

9. The applicant must submit any maps, computations or other material required by the Federal Emergency Management Agency (FEMA) to revise the Flood Insurance Study and/or Flood Insurance Rate Maps, when notified by the Floodplain Administrator, and must pay any fees or other costs assessed by FEMA for this purpose.

F. Placement of Structures

1. All buildings and structures shall be constructed and placed on the lot so as to offer the minimum obstruction to the flow of water and shall be designed to have a minimum obstruction effect upon the flow and height of floodwater.

(i) Whenever possible, structures shall be constructed with the longitudinal axis parallel to the direction of flood flow and,

(ii) So far as practicable, structures shall be placed approximately on the same flood-flow lines as those of adjoining structures.

G. Anchoring

1. All buildings and structures shall be firmly anchored in accordance with accepted engineering practices to prevent flotation, collapse, and lateral movement, thus reducing the threat to life and property and decreasing the possibility of the blockage of bridge openings and other restricted sections of the watercourse.

2. All air ducts, large pipes, and storage tanks located at or below the Base Flood Elevation shall be firmly anchored to resist flotation.

3. All manufactured homes shall be anchored in compliance with the requirements of 42 CSR Series 19, Sections 10.1, 10.2, and 10b et seq.  Anchoring shall be adequate to resist flotation, collapse, or lateral movement.  Methods of anchoring may include but are not limited to the over-the-top and frame ties, attached to foundation elements, such as the following:

(i) Over-the-top ties shall be provided at each of the four corners of the manufactured home, with two additional ties per side for manufactured homes less than 50 feet long.

(ii) Frame ties shall be provided at each corner of the home with five additional ties per side at intermediate points, with manufactured homes less than 50 feet long requiring four additional ties per side.

(iii) All components of the anchoring system shall be capable of carrying a force of 4,800 pounds.

(iv) Any additions to a manufactured home shall be similarly anchored. This requirement is in addition to applicable State and local anchoring requirements for resisting wind forces.

 


H. Flood Protection Setback

1. A Flood Protection Setback equal to twice the width of the watercourse channel measuring from the top of one bank to the top of the opposite bank or 50 feet, whichever is less, shall be maintained from the top of the banks of all watercourses. To reduce erosion, natural vegetation shall be maintained in this area.  Where natural vegetation does not exist along the watercourse and conditions for replanting are suitable, high priority shall be given to planting vegetation in the setback area to stabilize banks and enhance aquatic resources.

2. Necessary public works and temporary construction may be exempted from this subsection.

3. The Floodplain Administrator may consider an appeal to the Flood Protection Setback requirement if the applicant demonstrates that it is impossible to allow any development without encroachment into the Flood Protection Setback area.  The appeal conditions shall be the minimum necessary and shall be made only after due consideration is given to varying other siting standards, such as side, front and back lot line setbacks.
 
I. Storage

1. No materials that are buoyant, flammable, explosive, or in times of    flooding could be injurious to human, animal or plant life, shall be stored below Base Flood Elevation.

2. Storage of other material or equipment may be allowed if not subject to major damage by floods and firmly anchored to prevent flotation or readily removable from the area within the time available after flood warning.

3.  Due to the potential of masking the natural elevation and making it more difficult to enforce this ordinance, material that resembles “fill” material shall not be considered “storage” material for purposes of this subsection. 

J. Utility and Facility Requirements

A. All new or replacement water systems whether public or private, shall be designed to minimize or eliminate infiltration of floodwaters into the systems.

B. All new or replacement sanitary disposal systems, whether public or private, shall be designed to minimize or eliminate infiltration of floodwaters into the systems and discharges from the systems into floodwaters.

C. All other new or replacement public and/or private utilities and facilities shall be located and constructed to minimize or eliminate flood damage.

D. Onsite waste disposal systems shall be located to avoid impairment to them or contamination from them during flooding.

K. Drainage

      Adequate drainage shall be provided to reduce exposure to flood hazard.

L.  Backflow Preventers

Back flow prevention valves should be used for all enclosed structures with sewage or drainage facilities located in the floodplain.

ARTICLE VII - ADMINISTRATION

Designation of Floodplain Administrator

The Emergency Services Director is hereby appointed as Floodplain administrator to administer and implement this local law by granting or denying floodplain development permits in accordance with its provisions.

Section 7.1 Development Permits and Site Plan Approval Required

It shall be unlawful for any person, partnership, business, or corporation to undertake or cause to be undertaken, any development or the new construction, substantial improvement, repair of substantial damage, the placement or relocation of any structure (including manufactured homes) within Clay County, unless a permit application and standard site plan has been completed, and a permit has been obtained from the Floodplain Administrator.  In addition, where land that is either partially or fully in the regulatory floodplain is to be subdivided, utilized for a manufactured home park or subdivision or otherwise developed, a detailed site plan must be submitted to, and approved by, the Floodplain Administrator prior to any development.

Section 7.2 Approval of Permits and Plans

The Floodplain Administrator shall review, or shall cause to be reviewed; all permit applications and plans in order to determine whether proposed building sites are reasonably safe from flooding.

All permits and plans shall be approved only after it has been determined that the proposed work to be undertaken will be in conformance with

 

advertisements
 